| Projektinformationen | |
| Region | China |
| Unit Type | Modular Units |
| Sector | Infrastructure Projects |
| Quantity | 560 units |
| Applications | Offices, Accommodations, Conference Rooms, Restaurants |
| Year | 2024 |
1. Project Background: A key power source supporting the national “Desert, Grassland, and Wasteland” New Energy Base and the “Longnan Power to Zhejiang” initiative, with a total investment of 8 billion yuan, an annual power generation capacity of 9 billion kWh, and a peak workforce of 3,600 construction workers
2. Purpose: Construction worker dormitories, project office, conference rooms, training rooms, cafeteria, medical first-aid station, security office, restrooms/shower facilities
3. Tight Schedule: Construction begins in February 2024; both units to be commissioned by the end of 2026; rapid construction and zero delays
Rapid deployment of prefabricated units (mainstay for the dormitory area)
4. Specifications: Standard domestic dimensions: 6055 × 2990 × 2896 mm
5. Installation: Factory prefabrication with on-site bolted assembly; installation of 560 units completed in 15 days
– Reusability: Relocated as a whole after project completion; reusable at the next construction site
6. Large-scale Delivery and Cost Optimization
Production Capacity: 560 units produced within 30 days to ensure meeting critical milestones
Logistics: Transported in batches via full truckloads to reduce long-distance freight costs across the Gobi Desert
Cost: Compared to traditional color-coated steel panel buildings, total costs reduced by 20% and construction time shortened by 50%
Safety: Comprehensive quality control throughout the process, zero safety incidents, and recognized by the client as an “Excellent Supplier”